Chicago Water Main Project
Due to some upcoming work on the Chicago Avenue Water Main Project, Chicago Avenue will need to be reduced down to a single lane again on Friday, July 6th. The work is expected to take the majority of the day, however, crews will continue to work efficiently in an effort to minimize the disruption and to open two lanes on Chicago Avenue as quickly as possible. Thank you for your cooperation during this time.
Chicago Avenue Resurfacing Project
As construction on the Chicago Avenue Water Main Improvement Project wraps up, construction will soon be starting on the Chicago Avenue Resurfacing Project. Work on the resurfacing project will start with excavation for the curb bump-outs and rain gardens. These will be completed in the order of Bonnie Brae, Jackson Ave, Forest Ave, and Keystone Ave. For further details and ongoing construction updates, feel free to visit the Village’s construction website at www.vrf.us/construction